BP

Construction & Relocation of tank

 Location: Europoort, The Netherlands

Duration of project: June 2018 - July 2020

Volume: €4,3 mio

Scope

  • Engineering
  • Civil works
  • Tank Construction
  • Mechanical works
  • Relocation of tank
  • Managing subcontractors

To expedite the project timeline, the new tank was initially constructed on a temporary foundation. Subsequently, the old tank was dismantled, and the preexisting foundation underwent refurbishment. Upon the new tank's assembly, it was then transferred using SMPT's to its original foundation. Verwater oversaw all facets of the project, encompassing tank construction, civil tasks like foundation restoration, installation of heating coils and mixers, tank relocation to the updated foundation, hydrotesting, and subcontractor coordination.