BP Marpol

Engineering, Procurement & Construction

 Location: Adana, Turkey

Capacity: 13.000 m3

Project completion time: 23 months

Completion date: November 2014

Turnkey delivery of Oily Water Slop Tanks and Bilge Water Reception and Treatment Facility, including piping, structural, and E&I. All process, civil, mechanical, piping, electrical and instrumentation detail engineering was performed by Verwater’s in house engineering department in Istanbul. The project was completed without any safety incident.