MOT

Removing, Construction and installing DDFR

 Location: Europoort, The Netherlands

Capacity: 360.000 m³

Project completion time: 5 years

Project completion date: 2018 - 2023

Volume: €20 mio

Scope

  • Engineering
  • Prefab construction works
  • Mechanical works

In 2023 we've completed a project involving the replacement of double-deck floating roofs in 10 tanks. Verwater was responsible for the engineering, the removing of the old DDFR, the prefabrication and installing of these DDFR, the placing of rollingladders and the performance of hydrotest.