ETT3 Overview
March 30 2012

Completion ETT 3

Early 2010 there was an integrated team created between VTTI, Verwater and several subcontractors. The team created an objective to complete the ETT III project in January 2012. To achieve that goal, in October 2011 the project accelerated due to double shifts, day and night.  

Around 700 workers were working daily on site, seven days a week. The challenge was to perform the works of all different disciplines in a safe way and we have accomplished that goal successfully. The target date was achieved and at this moment we are in the latest stage of the project: testing & commissioning.  

This means that from now on, the ETT III terminal is a live plant and we have to work according the ETT III work permit system to perform the last activities. These last activities like painting, landscaping and other minor works will be finalized around April 2012.

Vergelijkbare artikelen

25 Maart 2024

Continuïteit en Samenwerking

Binnen Verwater Industrial Services streven we naar langdurige relaties met onze klanten, waarbij onze projectmanagers en contractmanagers een essentiële rol spelen. Tegelijkertijd erkennen we ook de waarde van onze ervaren collega's die op enig moment toe zijn aan welverdiende rust, zoals VUT of pensioen.

22 Maart 2024

Partner Awards TotalEnergies

Gisteravond hebben wij maar liefst twee Partner Awards van TotalEnergies aan onze prijzenkast mogen toe voegen! 🏆🏆 De awards zijn gewonnen door onze civiele ploeg voor Categorie A > 5.000 uren (klusjescontract) en voor Categorie B/C > 25.000-50.000 uren (burgerlijke bouwkunde). Trots op onze mannen! 💪

15 Maart 2024

Vrouwendag bij Verwater!

Afgelopen vrijdag 8 maart was het Internationale Vrouwendag en dat is ons niet ontgaan. Van een ontbijt in Rotterdam tot een lunch in Amsterdam, Groningen en Antwerpen, we hebben de vrouwen flink in de watten gelegd. Een dag vol plezier en gezelligheid!