Schermafbeelding 2024 03 20 om 10.32.35
MOT – Removing, Construction and installing DDFR

MOT

  • Location: Europoort, The Netherlands
  • Capacity: 360 000 m3
  • Project completion time: 5 years
  • Project completion date: 2018 – 2023
  • Volume: €20 mio
  • Scope:
    • Engineering
    • Prefab construction works
    • Mechanical works

At 10 tanks at MOT we are recently replacing double deck flooting roofs. Verwater is responsible for the engineering, the removing of the old DDFR as well as the construction (prefab) and installing of these DDFR, the placing of  rollingladders and the performance of hydrotest.

VerwMot (1) (Middel)